10/05/12 Bill Masura, Phend & Brown Project Manager for the Plymouth Street Projects said Wednesday after they are planning on beginning work on Plymouth City Streets next Monday, October 8th.
The following streets will be affected:
Center Street – Monroe to Jackson
Ewing Street – Michigan to Bayless
Madison Street – Eighth to Dead End
Monroe Street – Michigan to Magnetic Pkwy
Garro Street – Fifth to Washington
Richter Road – Jefferson to Baker
These areas will be closed to traffic during work hours except for Madison Street which local traffic will be allowed to pass. All work is planned to be completed by end of the day Wednesday, October 10th except for the striping work on Richter Road which will be later in the week or early the following week.