Plymouth_Logo_2014Last week City Engineer Rick Gaul presented a second round of street projects for the 2015 season.

Projects added to the current list include VanVactor Drive from Pioneer Drive to the 2015 patch, the intersection of Beerenbrook and Washington Streets.  The project will be north on Beerenbrook to the alley south of Jefferson Street and east on Washington Street to the corporate limits.

Jim Nelson Drive from Oakhill Avenue south to the corporate limits will be milled and filled.

In Centennial Park Chuck Glaub Drive, also known as Baseball Lane will be completed in three phases. Phase one will be from Becknell Drive north to the curve.  Phase two of the project will be from the curve to Randolph Street and phase three will the B League parking loop.  Bids and funding amounts will determine which phases will be performed.

The Plymouth Board of Public Works and Safety unanimously approved the list of projects.