road_workThe Plymouth Board of Public Works and Safety recently approved the request to restrict parking for the Spring Micro Surface and curb ramp projects.

Pavement Solutions Inc from Middletown, IN was to sole bidder on the project with a bid of $128,625.86.   They will begin work on Monday, May 21st.

Parking restrictions will begin on Monday, May 21st through June 15th for curb ramps and sidewalk repairs and June 18th through July 9th for the micro surface placement.  The restrictions will be Monday through Friday from 6 a.m. until 8 p.m. on Webster Avenue from South Michigan Street to Angle Street.

A lane restriction will happen on South Michigan Street near Webster Avenue for new curb ramp upgrades.  The contractor will have to restrict traffic on South Michigan Street while working on the curb project.