City Engineer Discusses Projects

September 14, 2010
news_logo

City Engineer Rick Gaul was notified Monday afternoon that the intersection of Oak and Hoham Drives will be closed beginning Wednesday morning, September 15th. NIPSCO will be working in the intersection to lower the gas main approximately 8 to 10 feet under the pavement.  The project is expected to take several days and is...
Read More »

Earth Moving on Pioneer Moves North of RR

June 10, 2010
pioneer

06/10/10   Ron Wireman, Construction Engineer from DLZ for the Pioneer Drive Extension and Improvement Project updated the county commissioner on the progress of the work.  The dirt moving work continues on the new Pioneer Drive project and while the work is still officially “on schedule”, according to Wireman, utility work could soon cause...
Read More »